This UK solar installation checklist helps you check an installer, confirm planning and electrical requirements, prepare for DNO processes, and collect the documents you will need after commissioning. Keep it with your project paperwork and return to it whenever the system, property or relevant rules change.
Overview
A solar installation is more than fixing panels to a roof. A compliant project also involves structural checks, electrical design, possible planning or building-control considerations, grid connection requirements, commissioning tests and a clear handover. The exact process depends on the property, system size, location, equipment and whether you are adding a battery, EV charger or other generation.
Use this checklist as a sequence rather than a substitute for professional advice. Ask the installer to explain which items they will handle and which remain your responsibility. Requirements can differ across England, Scotland, Wales and Northern Ireland, and local authorities or network operators may apply their own processes. Check the latest official guidance before work begins.
A useful project file should contain the quotation, design documents, correspondence, approvals, certificates, warranties, photographs and commissioning information. Keeping these records in one place makes future maintenance, insurance reviews, property sales and system upgrades easier.
Checklist by scenario
Before requesting quotations
- Record your objectives. Decide whether the main aim is reducing imported electricity, exporting surplus generation, supporting an EV charger, adding battery storage or improving resilience during outages. A system designed around one objective may not be ideal for another.
- Gather property information. Note the roof age, construction, shading, orientation, areas available for panels, location of the consumer unit and likely cable routes. Tell the installer about planned roof work, extensions, heat pumps or an EV charger.
- Check ownership and permissions. If you rent, lease the property, share a freehold or live in a managed building, obtain written permission before accepting a design. Flats and leasehold properties may involve additional roof, access and alteration agreements.
- Compare like with like. Ask each installer to specify panel and inverter models, battery capacity if included, estimated annual generation, assumptions about shading, monitoring arrangements, workmanship cover and exclusions. Avoid comparing headline panel capacity alone.
When choosing an installer
- Verify credentials. Check whether the business is currently certified under the relevant MCS scheme if you want an MCS-certified installer and may need certification evidence for an export arrangement or other purpose. Confirm the company name and scope rather than relying only on a logo in an advert.
- Ask who is responsible for each approval. The contract should state whether the installer handles DNO notifications or applications, planning enquiries, building-control matters and any required structural assessment.
- Review the design, not just the sales estimate. Look for panel layout, roof access, cable routes, isolators, inverter location, battery ventilation and protection, earthing arrangements, and the proposed connection to the existing electrical installation.
- Check aftercare. Confirm how faults are reported, who provides monitoring support, what happens if a component fails, and whether maintenance or inspection is recommended. A low initial price may not include every document or service you expect.
Before installation starts
- Confirm the contract and final design. Do not rely on a verbal promise to add a battery, change the panel arrangement or provide backup power. Put equipment, performance assumptions and variations in writing.
- Clarify planning status. Some domestic solar installations may fall within permitted development or equivalent arrangements, but restrictions can apply to listed buildings, conservation areas, protected properties, unusual roof designs and ground-mounted systems. Ask the installer or local planning authority what applies to your property.
- Check building-control responsibilities. The work may involve structural and electrical elements. Confirm whether the installer will provide any required certification or whether you must contact building control separately. Keep written confirmation of the route taken.
- Confirm DNO arrangements. Solar and battery systems connected to the public electricity network may require notification or approval from the distribution network operator. The installer should identify the relevant DNO and explain whether the project uses a notification route or needs approval before installation. Do not assume that a previous approval covers a new battery, inverter or larger system.
- Plan safe access. Agree how scaffolding, roof access, parking, power isolation and weather delays will be managed. Keep children, visitors and pets away from work areas.
At installation and commissioning
- Check that installed equipment matches the agreed design. Record model numbers and serial numbers for panels, inverters, batteries, gateways and charge points.
- Ask for a clear explanation of controls. The installer should show you how to use the inverter and solar monitoring app, interpret alarms, change permitted settings and safely isolate the system.
- Confirm commissioning tests. Request evidence that the electrical installation, protective devices, generation equipment and battery system have been tested in line with applicable requirements. The completion pack should identify any limitations or outstanding work.
- Inspect the finished work from ground level. Check for visible cable damage, poorly supported conduits, water-management issues, loose components, obstructed access or equipment installed contrary to the agreed location. Raise defects promptly rather than waiting for the first bill.
At handover
- Collect the final electrical certificate or applicable completion documentation.
- Obtain the MCS certificate or other installation evidence promised in the contract, where applicable.
- Keep DNO correspondence, approval or notification records and any conditions attached to them.
- Store product manuals, datasheets, warranty terms, installer workmanship terms and insurance-backed guarantees if supplied.
- Save the final design, single-line diagram, panel layout, cable routes, photographs and equipment serial numbers.
- Record the monitoring account details and confirm that ownership or access can be transferred if you sell the property.
- Ask how to shut down the system in an emergency and who to contact for faults.
What to double-check
DNO approval is not the same as an installer promise. Ask for the actual notification or approval reference and read any export limitation or operating condition. If you later add a battery, EV charger or replacement inverter, ask whether the change affects the original grid connection.
Export arrangements need evidence. If you plan to join a Smart Export Guarantee tariff, check what your chosen electricity supplier requires and retain the installation and certification documents. The process and evidence requirements can change, so review the supplier’s current terms rather than relying on an old application guide. Our SEG tariff checklist covers export arrangements and annual reviews.
Battery systems need their own review. Confirm the battery’s location, ventilation, protection, usable capacity, warranty conditions and backup-power behaviour. A standard grid-connected battery may not keep essential circuits running during an outage unless the system has been specifically designed for that purpose. See the solar battery safety checklist for record-keeping and emergency planning.
Roof condition matters. If the roof is near the end of its serviceable life, ask whether repairs or replacement should happen before installation. Removing and refitting panels later can affect costs, warranties and access; use the roof replacement checklist when planning work.
Insurance and future sale documents should be complete. Tell your insurer about the installation where required by its policy and keep the completion pack. Buyers, conveyancers and lenders may ask for certificates, warranties and grid records. The solar property handover guide can help when ownership changes.
Common mistakes
- Choosing an installer from a panel price without checking the full scope of work.
- Assuming permitted development applies without checking property-specific restrictions.
- Installing equipment before confirming the DNO route.
- Failing to disclose a future battery, EV charger or other planned electrical load.
- Accepting a handover that contains manuals but no certificates, test records or serial numbers.
- Not checking who owns the monitoring account or how access will be recovered.
- Ignoring roof condition, cable routes, inverter heat, battery access or emergency isolation.
- Relying on estimated generation as a guarantee of savings or export income.
When to revisit
Review this checklist at four points: before signing a quotation, immediately before work begins, at commissioning, and whenever the system or property changes. Recheck the relevant government, local-authority, certification-body, network-operator and electricity-supplier guidance before relying on an old form or process.
Revisit the documents if you add battery storage, an EV charger, a heat pump or extra panels; replace an inverter; alter the roof; change your export tariff; renew home insurance; or sell the property. At each review, confirm that the installed equipment, DNO records, certificates, warranties and monitoring access still match reality.
Practical final step: create a digital and paper project folder, use the headings in this article as a contents list, and do not mark the installation complete until every promised document has been received and explained. That small habit can prevent avoidable problems when the system needs maintenance, an upgrade or a future handover.